PROCESS MAPPING & IMPROVEMENT — LANTERN PROJECT PACK Version 1 | Original fictional teaching material | 2026-10-30 All names, rules, requests and timestamps below are invented. “Log-supported” means supported within this supplied exercise, not witnessed in a real service. Use paper or copy this plain-text file into an existing local editor. No account, paid diagramming tool, personal records, outreach or live equipment is needed. No degree, qualification, professional safety advice or savings guarantee. HOW TO USE THE PACK Attempt sections A–G before reading the MODEL. Keep an initial attempt and a revision log. The proposed course workload is 20 hours, not a measured promise: approximately 6 hours reading/examples, 6 hours practice/checks, 6 hours project, and 2 hours revision. Record actual time separately. Completing a written map is not proof that a real workflow works or that equipment is safe to issue. FIXTURE P1 — STATED PROCEDURE, NOT PROOF OF EXECUTION Lantern lends portable display stands in this imaginary case. One request is the unit of analysis. Receipt begins the boundary. A ready notice or communicated, recorded refusal ends it. Collection, use and return are outside this map. Roles: borrower, coordinator, designated safety reviewer, preparation volunteer. Required information: item, requested date and confirmation of completed borrower orientation. The coordinator checks completeness, then eligibility. Unknown orientation needs clarification; do not treat it as either approved or a proven refusal. Ineligible requests receive a reasoned refusal. Eligible requests go to the reviewer for a safe-to-loan condition decision tied to the request and stand. Preparation may start only after recorded approval. An unclear or missing approval pauses preparation for clarification. Prepared requests receive a ready notice. No automatic timeout or permission to bypass review is supplied. The paper route remains available; this case does not require a digital form. FIXTURE E1 — SYNTHETIC EVENT LOG All timestamps are in one invented local clock, YYYY-MM-DD HH:MM, with no clock change. Per-request active intervals do not overlap. A completed preparation interval includes the ready notice at its endpoint. No other active tasks occur for L1 or L2 in this fixture; L3 has deliberately incomplete event coverage. L1 2030-02-04 09:00 receipt; required information supplied 09:00–09:10 coordinator completeness and eligibility check; eligible 09:10 sent for review 09:30–09:40 designated safety review; recorded approval at 09:40 09:45–10:00 preparation; ready notice at 10:00 L2 2030-02-04 09:00 receipt 09:00–09:10 coordinator check; requested date missing; clarification sent 2030-02-05 09:10 borrower supplies date 09:10–09:15 coordinator recheck; complete and eligible; sent for review 09:30–09:40 designated safety review; recorded approval at 09:40 09:45–10:00 preparation; ready notice at 10:00 L3 2030-02-04 11:00 receipt 2030-02-04 12:00 ready notice No task intervals, completeness result or review decision supplied. Unknown is not zero and does not prove that review was skipped or performed. SIMULATION CARDS S1 — NOT ACTUAL TRIAL RESULTS Card A: item supplied; date supplied; orientation confirmed; review pending. Card B: item supplied; date missing; orientation confirmed; review pending. Card C: item supplied; date supplied; orientation unknown; review pending. Card D: item missing; date supplied; orientation confirmed; review pending. Do not release any card to preparation without the required approval. The cards exercise the intake and clarification logic, not real equipment safety. OPTIONAL FICTIONAL COMPARISON C1 A separate invented example reports 2 complete packets out of 4 baseline packets and 3 out of 4 trial packets. No timestamps, random assignment, matching, harm measure or actual test is provided. This is not a result produced by cards S1. Use only to practise proportions and limitations; do not invent causal savings. A. BOUNDARY AND CURRENT MAP — EDITABLE TEMPLATE Process name/version: [ ] Question: [ ] Unit: [ ] Start event: [ ] Terminal outcomes: [ ] Exclusions: [ ] Process owner role: [ ] Legend: [action] WAIT (endpoint); arrows show sequence, not duration. Current procedure map: [ ] -> < > --Yes--> [ ] -> ( ) --No--> [ ] -> WAIT -> [ ] Observed-log overlay (state which request supports each step): [ ] Do not label a procedure-required step as verified for every request. B. SWIMLANE/HANDOFF TABLE — ADD ROWS LOCALLY Step ID | Role | Action | Required input | Output/acceptance | Next step [ ] | [ ] | [ ] | [ ] | [ ] | [ ] Handoff owner: [ ] What proves transfer/acceptance, rather than merely sending? [ ] What happens if the packet or approval is missing? [ ] C. EVIDENCE TABLE — EDITABLE Claim | Source ID and exact event | Status | Limitation / next question [ ] | [ ] | [ ] | [ ] Statuses: log-supported, procedure-stated, proposed, unknown. Keep original fixtures unchanged and version any proposed process separately. D. DURATIONS AND FAILURE-CONTROL TABLES Request | Receipt | Endpoint | Active intervals | Active min | Elapsed min | Known gaps / unknowns [ ] | [ ] | [ ] | [ ] | [ ] | [ ] | [ ] Show arithmetic and units. For incomplete intervals use unknown, not zero. Failure | Possible effect | Current/proposed control | Owner/trigger | Response | Evidence needed [ ] | [ ] | [ ] | [ ] | [ ] | [ ] E. FUTURE MAP AND TRADE-OFFS — EDITABLE Proposal/version: [ ] Changed nodes only: [ ] Future map (label PROPOSED): [ ] Change | Mechanism | Predicted benefit | Possible harm | Retained protection | Test evidence [ ] | [ ] | [ ] | [ ] | [ ] | [ ] Alternative design and why it might be preferable: [ ] No claimed achieved savings without actual evidence. F. REVERSIBLE TEST PLAN — EDITABLE Question: [ ] Prediction, stated before test: [ ] Scope/cards/version: [ ] Owner and authority limits: [ ] Steps: [ ] Outcome measure and boundary: [ ] Process numerator/denominator: [ ] Balancing measures: [ ] Missing-data/open-case handling: [ ] Stop/pause trigger: [ ] Rollback steps: [ ] Simulation observations (leave blank until performed): [ ] Unexpected observations: [ ] Decision: revise / another test / abandon, with reasons [ ] Real-world pilot would need: [ ] G. RECOMMENDATION, REVISION AND SELF-REVIEW Write a one-page recommendation that names the question, evidence, uncertainty, proposal, trade-offs and test decision. Add one acceptable alternative. Revision log: initial claim | reason/evidence for change | revised claim. Time log: activity | estimated minutes | actual minutes | reason for difference. A second person may review the pack, but no recruitment is required. A solo learner can trace each card and compare with the model below. This is self-review, not independent real-world validation, external grading or a certificate. ================ MODEL — READ AFTER YOUR ATTEMPT ================ MODEL A: BOUNDARY Question: how can avoidable incomplete packets be reduced without bypassing the required review or making submission inaccessible? Unit: one request. Start: receipt. End: ready notice or communicated, recorded refusal. Excludes collection/use/return. Proposed process owner: coordinator; this does not transfer the reviewer's decision authority. MODEL CURRENT MAP (P1 procedure; not verified execution for every request) (Receipt) -> Coordinator [Check item/date/orientation entry] -> No -> [Ask for missing entry] -> WAIT for reply -> [Recheck] Yes -> [Evaluate eligibility] -> Unknown -> [Clarify] -> WAIT -> [Re-evaluate] No -> [Communicate and record refusal] -> (Refusal) Yes -> [Send identified packet to reviewer] -> WAIT for review -> Reviewer [Required safe-to-loan decision] -> Clarify -> [Resolve evidence gap] -> [Re-review] No -> [Communicate and record refusal] -> (Refusal) Yes -> [Record matching approval] -> Preparation volunteer [Verify matching approval and prepare] -> [Send ready notice] -> (Ready) If approval is absent or ambiguous: pause preparation and return to reviewer. No automatic closure after a waiting period is invented. L1 supports the complete eligible/approved/prepared path. L2 supports an initial missing-date loop and later approval/preparation. L3 does not verify these steps. MODEL B: LANE/HANDOFF ROWS B1 | Borrower | Supply request | item/date/orientation | identified request | C1 C1 | Coordinator | Check and evaluate | request | complete/eligible packet or clarification/refusal | R1 or B1 or end R1 | Reviewer | Required safety decision | matched packet and condition evidence | recorded approval/refusal/clarify | V1 or clarification/end V1 | Preparation volunteer | Check matching approval, prepare, notify | approved identified request | ready notice | end “Sent” proves a send event only. Review start and recorded decision have separate evidence. Preparation never treats an unacknowledged message as approval. MODEL C: EVIDENCE TABLE Safety review is required | P1 | procedure-stated | not proof of every execution L1 review took 10 min | E1 L1 09:30–09:40 | log-supported | synthetic one-case interval L2 had missing date | E1 L2 initial check | log-supported | not every request L3 review happened | no supplied record | unknown | request original review evidence in a real authorised inquiry Prompt reduces returns | proposal | proposed | no observed effect yet All delays are reviewer fault | none | unknown/unsupported | gaps cannot establish cause or blame MODEL D: DURATION CALCULATIONS L1 active: (09:10-09:00) + (09:40-09:30) + (10:00-09:45) = 10 + 10 + 15 = 35 min. Elapsed: 10:00-09:00 = 60 min. Gaps: 20 + 5 = 25 min. Check: 35 + 25 = 60. L2 active: 10 + 5 + 10 + 15 = 40 min. Elapsed: day 1 09:00 to day 2 10:00 = 25 h = 1,500 min. Gaps: day 1 09:10 to day 2 09:10 = 1,440 min; then 15 + 5 min. Total gaps = 1,460 min. Check: 40 + 1,460 = 1,500. L3 elapsed: 12:00-11:00 = 60 min. Active work and gap breakdown unknown. Known-case mean active = (35 + 40) / 2 = 37.5 min, covering 2 of 3 requests. Do not divide 75 by 3: that would silently treat L3 as zero. The independent 10-min work + 24-h wait + 15-min work mini-case totals 25 active min and 1,465 elapsed min; it is not L2. MODEL FAILURE-CONTROL ROWS Missing date | clarification/delay | prompt + retained completeness check | coordinator before handoff | ask for missing date | count incomplete packets. Unmatched approval | wrong or unsupported preparation | verify request/stand match | preparation volunteer before work | pause and clarify | matching record. Lost notice | borrower unaware of readiness | include notice in preparation completion | preparation volunteer at endpoint | verify notice record | send event. These are design controls, not guarantees. Do not remove the safety review. MODEL E: PROPOSED FUTURE MAP Add before submission: [Show item/date/orientation prompt; paper equivalent]. Keep all current-map decisions and routes. At coordinator handoff use a three-field packet checklist; do not repeat safety approval or merge it into completeness. Predicted mechanism: earlier awareness may reduce missing-field clarification. Trade-offs: borrower effort, coordinator checklist time, possible confusion about unknown orientation. Preserve clarification, paper route and required review. No duplicate copying step is removed: the log never established one existed. Alternative: keep current form and offer coordinator pre-check support. This may help people who need assistance, but consumes staff time and may create a queue. Test separately so the effect of each design is not conflated. MODEL F: REVERSIBLE TEST PLAN Question: can the prompt expose the S1 omissions without falsely approving a card? Prediction: A passes completeness, B and D need missing-field clarification, C needs orientation clarification; none reaches preparation while review is pending. Scope: four synthetic cards, one learner, paper simulation, proposal version 1. Procedure: trace each card from receipt through the proposed map; log each exit and any ambiguous instruction. Keep original P1 and the current map unchanged. Owner: learner for the simulation only; no authority over real equipment. Simulation process measure: correct clarification route among four cards, with individual decisions recorded. This is not a real submission-completeness rate. Future authorised pilot outcome: receipt-to-ready/refusal elapsed time per request. Future process measure: complete packets / all submitted packets, report both counts. Balancing: submission difficulty, coordinator effort, open cases, missing/mismatched approval evidence. Record unknown times explicitly, not as zero. Include requests still open at the observation cut-off rather than omitting them from the report. Stop: any route permits preparation without review or prevents paper submission. Rollback: withdraw proposed prompt, restore the unchanged prior procedure, retain observations, investigate and revise before another simulation. Expected card trace is a model, not a claimed learner or device test result: A complete -> eligibility check -> required review pending. B missing date -> clarification -> recheck when supplied. C orientation unknown -> clarification -> re-evaluate; no approval inferred. D missing item -> clarification -> recheck when supplied. Actual observation fields remain blank until the learner runs the simulation. No real response-time or safety-outcome claim can follow from these cards. MODEL G: ONE-PAGE RECOMMENDATION Lantern should consider testing a clearer intake prompt while preserving its required safety review. The bounded question concerns incomplete packets between receipt and ready/refusal notice, not the whole equipment lifecycle. P1 states the review requirement. E1 provides two detailed synthetic cases: L1 has 35 active and 60 elapsed minutes; L2 has 40 active and 1,500 elapsed minutes, including a missing- date loop. L3 has 60 elapsed minutes but insufficient task evidence. These cases cannot establish a real organisation's performance, causes of all waiting or savings from a change. The proposed prompt makes item, date and orientation requirements visible before submission and retains a paper equivalent. Its expected mechanism is fewer missing entries, not faster or weaker safety decisions. The coordinator's completeness and eligibility checks remain separate from the reviewer's approval. Preparation stays gated by a matching recorded decision. Potential costs include more borrower reading and coordinator checklist work; these must be observed rather than assumed away. Coordinator pre-check assistance is an acceptable alternative for testing, with its own staffing burden. First trace four synthetic cards against the proposed map and record the actual simulation outcomes. Pause and revise if a card bypasses required review or lacks a clarification route. Preserve the old map so rollback is immediate. Only a later, authorised real pilot could supply evidence about receipt-to-notice time, incomplete packet rates, effort and access. Such a pilot should retain unresolved cases and unknown timestamps, report denominators and compare predictions with observations. Do not convert the separate fictional 2/4 versus 3/4 example into a claimed result: it is a 25-percentage-point difference, not evidence of causation or reliable savings. The defensible next decision is a bounded test and review, not deployment of a supposedly proven improvement. ALTERNATIVE ACCEPTABLE RECOMMENDATION Retain the form and test an optional coordinator pre-check instead of the new prompt. Explain the access benefit hypothesised, record staff effort and queueing, and preserve the same review gate. This can meet the rubric if the evidence and trade-offs are explicit; choosing the prompt is not the only correct answer. ANALYTIC RUBRIC — 100 POINTS, SELF-REVIEW ONLY 1. Boundaries/current map, 25: explicit unit/start/end/exclusions (10); complete, labelled branches and roles (10); no invented current steps (5). 2. Evidence/uncertainty, 20: claims tied to P1/E1 (10); L3 unknowns and scope limits retained (10). 3. Waiting/rework/controls, 20: correct reproducible duration arithmetic (10); required review and specific failure responses preserved (10). 4. Future-state trade-offs, 20: separately labelled proposal and mechanism (10); access/burden concerns and a defensible alternative (10). 5. Testable evaluation, 15: measures and denominators (5); reversible scope, stopping rule and rollback (5); predictions separated from observations (5). For each subcriterion: full points if explicit and consistent, half if present but incomplete, zero if absent or contradicted. Revise before treating the pack as ready if it removes the safety gate, invents L3 times, claims achieved savings without a test, or presents this synthetic exercise as real operational evidence. A numeric self-score is not a qualification or externally assessed result. SOURCE/RIGHTS RECORD All case prose, maps, cards, templates, model answers and questions in this pack are original for this course. No external worksheet, diagram or clinical example is copied. Primary readings checked 2026-10-30: AHRQ All Workflow Tools: https://digital.ahrq.gov/health-it-tools-and-resources/evaluation-resources/workflow-assessment-health-it-toolkit/all-workflow-tools IHI Testing Changes: https://www.ihi.org/library/model-for-improvement/testing-changes Readings are link-only. No blanket reproduction licence or institutional endorsement is asserted. Their health-service context does not authorise real equipment decisions. The course can be completed without external downloads.